09/02/2026
Quick progress update on the new shop. Painting in the build-out has been completed, and the first of the warehouse walls got some color on it, too. I decided to go with a two-tone shop to help cut the glare off the vertical surfaces and make the work area a little bit easier to keep clean. The upper portion will the same color as the walls of the build-out for both continuity and light distribution. The T-bar ceiling grid is mostly in place, so now the electricians can install the balance of the office lighting. The tile in the showers has proven to be a bit of a PITA as most of the tiles in most of the boxes we’re receiving are broken and unusable. It’s a solvable problem, but it’s really slowed the progress on the bathrooms. Looking ahead, the warehouse paint should be completed in the next few weeks, and then it’s time to start grinding and leveling the floor for polishing and sealing. Once the warehouse floor is complete we can start moving in some of the new shop infrastructure items. It won’t be long now…