01/10/2026
Nice little wiring job started this week.
Absolutely amazing โladder/scaffoldโ
5/6m up in the air, on a 10x5ft platform ๐ช๐ช๐ช
Someone decided they needed all the head height below, so gave me NOTHING to go over the beams with, so up high, cables are put into a copex, and lower down, Iv had to drill out a 20mm hole and put a bush and locknut onto into them ๐๐ needs must!
Little bit of simple Tray work too, with an up and over main run.
Centre lights, wired and working with their PIRs
Rest of the lights part wired
Sockets Fully 1st fixed
Board is mounted readyโฆ
3 phase TPN
With the sites first SPD ๐ฌ thought it best, given itโs in a metal building ๐๐คฃ๐คฃ never mind the regs ๐คฃ๐คฃ
Long time since weโve done any warehouse work with Z perlins, takes me back to when burscough industrial estate was smaller, doing all the warehouses! ๐๐๐๐