Pump Installation & Start-Up Checklist
1- Read and understand the instruction manual.
2- Use a proper foundation.
The foundation should be rigid, level and clean of debris.
3 - Install the base on the foundation.
4 - Install the pump and the driver on the baseplate.
5 - Add the proper oil to the proper level in the bearing housings (pump, gear reducers, etc.)
6 - Check initial alignment.
7 - Ground the base to the foundation.
8 - Install piping. Read piping guidelines below.
9- Complete a second alignment check, and readjust piping as needed.
10- With the coupling element removed, complete a rotational check of the driver.
11- Verify correct pump settings.
12 - Install ancillary equipment.
13- Install coupling and/or insert.
14- Complete the pre-startup check procedure; fill and vent the pump and system, and check the system valve and component "lineup".
15- Recheck alignment to ensure that fluid weight in the piping didn't cause a change in the alignment.
16- Start the unit.
17- Check for proper indicators such as pressures, flows, temperature, vibration and noise.
18- Recheck alignment. Perform "hot alignment" if fluid is above 200°F.